Pawlowo 110/33 kV Substation, Poland

  • Provision, engineering and commissioning of the IEC 61850 Relion and MicroSCADA protection and control systems for the Pawlowo 110 / 33 kV substation in Poland. The Project involved the supply of all control and protection devices.  

Date: July 2012. Commissioning Feb. 2013. 

 

Margonin 110/33 kV Substation, Poland

      • Provision, engineering and commissioning of the expansion of the LON REF54x and MicroSCADA protection and control system for the Margonin 110 / 33 kV substation in Poland. The project involved the supply of all control and protection devices pertaining to the enlargement.  

Date: July 2012. Commissioning Feb. 2013

Margonin Wind Farm, non-technical summary - online document

 

  • Provision, engineering and commissioning of the expansion of the REF54x and MicroSCADA control systems of the Cernavoda 110 / 33 kV substation in Romania (pictured right). The project involved the supply of all control and protection devices pertaining to the enlargement.  
  • The substation control system is based on ABB MicroSCADA Pro technology using LON and DNP protocol communication with field equipment and IEC104 with two dispatch centres situated in Oporto and Bucharest.

Date: Nov. 2010. Commissioning stage 1 Feb. 2011. Commissioning stage 2 May 2011

Wikipedia: EDP Cernavoda Wind farm

 

Parralejos 220/33 kV Substation, Spain 

      • Engineering and commissioning of the expansion of MicroSCADA control system for the Parralejos 220 / 33 kV substation in Cadiz.

Date: Jan 2012. Commissioning July 2012

 

Maintenance of European Wind Farms

      • Contract: Engineering, maintenance and new control system projects 

Involves installation, programming, and implementing modifications to the existing control systems of various EDPR substations. All modifications are performed online and without the need to shut down systems. Tasks include: programming control & protection units; programming RTUs, SCADA engineering, setting up databases connected to control centres, etc. 

Architecture of Distribution Automation for HC Energía, Spain

Date: 15/01/2013 - 15/01/2016